Chimney Demolition Saw
The deconstruction of the BASF chimney with a height of 200 metres initiated development work on the chimney demolition saw by the MB Schornstein- und Betonabbruch company and LISSMAC. This development work was necessary because the immediate environment of the chimney prohibited the use of such traditional demolition techniques as blasting and chiselling, or concrete demolition with shears. The chimney demolition saw guarantees the safe demolition of the chimney with minimum impact on the immediate surroundings. The use of this special saw enabled the 200-metre high chimney to be demolished within 8 weeks, whereas demolition using traditional methods would have taken approximately 6 months.